t型牌制作应该按什么顺序去做?

所属分类:行业资讯 发布时间:2020-10-26 来源:http://www.jnguanggaopai.com/ 浏览量:18

1. 首要单立柱基础施工:在选定方位后需求放线并选用挖掘机进行开挖,基坑开挖完成后需在基坑四周做防护作业放置醒目标牌,保证附近行进车辆及络绎行人安全,其次是基坑底部处理,需求人工进行修正,底部修正完后下面进行钢筋绑扎并支撑地脚螺栓及法兰盘,这个时分需求检验基坑巨细及钢筋绑扎作业,检验合格后进行浇筑混凝土,一般选用自卸方法将混凝土输送至坑基内,有施工现场不允许混凝土搅拌车到现场时需求泵车输送,当混凝土输送完将外表处理平坦并坐上保护层,随后进行养护。
One The first single column foundation construction: after the orientation is selected, the setting out is required and the excavator is used for excavation. After the excavation of the foundation pit, the protection work should be done around the foundation pit, and eye-catching signs should be placed to ensure the safety of vehicles and pedestrians nearby. Secondly, the bottom of the foundation pit should be treated. After the bottom correction, the reinforcement should be bound and the anchor bolts and flange plates should be supported At this time, it is necessary to inspect the size of the foundation pit and the steel bar binding operation. After the inspection, the concrete is poured. Generally, the self unloading method is used to transport the concrete to the pit foundation. When the concrete mixer truck is not allowed to arrive at the construction site, the pump truck is required to transport the concrete. When the concrete is transported, the surface shall be treated flat and the protective layer shall be installed, and then the maintenance shall be carried out.
t型牌制作
Production of T-type brand
2. 其次t型牌制作半成品加工:单立柱采取加工厂加工为半成品后运至现场拼装焊接,螺旋管立柱出场前期在车间选用专业除锈设备进行除锈作业,铁红防腐,并对螺旋管钢立柱焊接法兰角筋板及衔接中空圆钢板,焊接完毕铲除焊缝药皮,做防腐,算计3遍,以保证螺旋管钢立柱漆面清洁。
Two Secondly, the semi-finished products processing of T-type brand: the single column is processed into semi-finished products by the processing plant, and then transported to the site for assembly and welding. At the early stage of the spiral pipe column, professional rust removal equipment was selected for rust removal, and iron red corrosion prevention was carried out. At the same time, the spiral pipe steel column was welded with flange angle rib plate and connecting hollow round steel plate. After welding, the welding seam coating was removed, and the anti-corrosion was done for 3 times to ensure the screw The paint surface of the steel column of the rotary tube is clean.
济南户外广告牌制作
3. 随后牌面及支撑钢梁施工:选用吊车将牌面钢架、支撑横担、牌面中心立柱,并对牌面钢架、支撑横担、牌面中心立柱钢结构定位组合、焊接加固。牌面钢结构组合焊接完毕,查看铲除焊缝药皮防腐补漏。装置压槽彩钢板应使压槽彩钢板长边垂直向下装置,以保证装置竣工的压槽彩钢板平坦漂亮。
3. Subsequently, the construction of deck and supporting steel beam: crane is used to install the deck steel frame, support cross arm and central column of plate surface, and the steel structure of plate surface steel frame, support cross arm and plate surface central column shall be positioned, assembled and welded. After the welding of the steel structure on the plate surface is completed, check and remove the coating of the weld to prevent corrosion and make up the leakage. The long side of the grooving color steel plate should be vertical downward to ensure that the finished grooving color steel plate is flat and beautiful.
4. 户外大型广告牌牌面吊装施工:立柱吊装时应留意落吊对丝精确,保证不咬丝。落吊到位,闭丝、紧丝应均匀进行,保证紧丝到位。再闭紧第二颗丝母牌面钢结构吊装。牌面钢结构吊装时应留意吊点结实,均匀平行上升。上升到一定高度均匀落吊至立柱衔接稍上端由地上人员配合对准衔接点精确落吊。落吊到位由地上人员调整广告牌方位。定点完毕由焊接人员登上立柱上端进行焊接作业。焊接结实撤吊。吊车撤离,焊接工人对焊口加固焊接。其他作业人员对作业场所整理。焊接作业、场所整理、完毕。由作业人员对竣工的广告牌做竣工复查。
4. Hoisting construction of outdoor large billboard surface: attention should be paid to the accurate wire setting during column hoisting to ensure no wire biting. Drop and hoist in place, close wire and tighten wire evenly to ensure wire tightening in place. Then close the steel structure of the second master plate. When hoisting the steel structure on the signboard, attention should be paid to the firmness of the lifting points, and the lifting points should be evenly and parallel rising. When it is lifted to a certain height, it shall be lifted to the upper end of the column connection, and the personnel on the ground shall coordinate to align the contact point for accurate lifting. The position of the billboard shall be adjusted by the personnel on the ground. After the fixed point is finished, the welding personnel shall mount the upper end of the column for welding operation. Welding is firm and lifting is removed. The crane was evacuated and the welding workers strengthened the welding joint. Other operators shall arrange the work place. Welding operation, site arrangement and completion. The operator shall review the completion of the completed billboard.
只有把上述所讲的内容设定好,我们的操作才算完成,如果您这边在后续的过程中有任何的问题,欢迎致电或者是在网站上边留言:济南户外广告牌制作http://www.jnguanggaopai.com
If you have any problems in the follow-up process, please call or leave a message on the website: Jinan outdoor billboard production http://www.jnguanggaopai.com